Armed Federal Agents Enter Warehouse in Puerto Rico to Seize Hoarded Electric Equipment

$
0
0

Kate Aronoff, writing for The Intercept, just broke some gobsmacking news on the power situation in Puerto Rico. After more than 100 days, electricity still has not been fully restored to the hurricane battered island and we now have a major clue as to why.

Apparently, a PREPA warehouse (Puerto Rico Electric Power Authority) named “Warehouse 5” has been hoarding the supplies to needed restore power.

On Saturday, a day after becoming aware of a massive store of rebuilding materials being held by the Puerto Rico Electric Power Authority, the U.S. federal government — the Federal Emergency Management Agency, the U.S. Army Corps of Engineers, along with their security detail — entered a Palo Seco warehouse owned by the public utility to claim and distribute the equipment, according to a spokesperson for the Corps.

Rumors of a tense standoff had been circulating on the island, but the encounter was confirmed to The Intercept in a statement from the U.S. Army Corps of Engineers. Asked if the federal officers were armed when they entered the warehouse, USACE spokesperson Luciano Vera said they were indeed accompanied by security detail and quickly began distributing the material after seizing it. Vera declined to say whether there was a confrontation at the entrance, saying only that PREPA officials ultimately toured the warehouse along with the feds:

Leadership responsible for restoring the Puerto Rico power grid and their security detail toured the warehouse in cooperation with PREPA. USACE conducted a full inventory and immediately sent out critical materials to contractors at work sites. USACE will continue to distribute critical materials from the site to contractors. The hope is to strengthen the partnership between PREPA and its restoration partners, while increasing visibility of the inventory of all materials on the island. PREPA has invited FEMA and the Corps to visit its warehouses anytime and to distribute material as needed.

snip

“Due to the size of the warehouse,” Vera said, accounting for everything contained therein is still underway days later. Among the materials recovered so far are “2,875 pieces of critical material to contractors” along with the sleeves of full-tension steel, a component of Puerto Rican electrical infrastructure required to erect new power lines. PREPA did not respond to The Intercept’s request for comment, though in a statement to the Associated Press, it rejected allegations that it had failed to distribute the warehouse’s contents. The AP only reported that “officials over the weekend also discovered some needed materials in a previously overlooked warehouse owned by Puerto Rico’s Electric Power Authority.” How they discovered them and how they were obtained is a story that has not been fully told.

snip

A security contractor who recently returned from Puerto Rico told The Intercept that crews of linemen brought down from the U.S. were frustrated about the lack of rebuilding materials, which made it virtually impossible for them to fix downed infrastructure. Paraphrasing conversations with the electric crews he accompanied, the source said one worker told him that “we just sat in the truck and watched a movie because we have nothing to do today. … Around Christmas, a lot of the power workers were saying, ‘We’re going on vacation because we couldn’t do our job because PREPA was making it so difficult.’” The source’s job involved escorting contractors tasked with reconstructing downed power lines; he was deployed on the island for over a month by a subcontractor of Cobra Acquisitions LLC, which in the fall received a $200 million contract with PREPA to repair its grid.

So much more at The Intercept.